Skip to main content
Freicore

Guides

How subcontractors track progress claims.

What progress claims are, why spreadsheets quietly lose money, and the workflow that keeps claimed, certified, and executed values connected.

Subcontractors track progress claims by keeping four records connected: the contract scope (the BOQ), measured physical progress against that scope, the cumulative amount claimed to date, and the amount the client has actually certified. A progress claim — also called a payment application or interim application — is the periodic statement of the value of work completed. Tracking it properly means being able to show, for any line of the contract, how much was executed, how much was claimed, and how much was certified — and to explain every difference between those three numbers.

The terms, untangled

Progress claim, payment application, interim application — different names for the same document: the periodic statement of the value of work executed, submitted to the client or main contractor for payment. The name varies by region and contract form; the mechanics do not.

Payment certificate — the response. The client or their quantity surveyor reviews the claim and certifies the value they accept for payment. It is rarely equal to the claim.

Cumulative and period values — claims are normally cumulative: the total value of work done to date, minus what was previously certified, gives the amount due this period. This is why a single wrong number carries forward into every future claim until someone finds it.

Why spreadsheet tracking breaks

Most subcontractors start with a spreadsheet, and most spreadsheets fail the same way — not loudly, but by slowly disconnecting the numbers that must stay linked:

None of these are calculation errors. They are record-keeping failures: the four records that must stay connected — scope, progress, claimed, certified — drift apart because nothing forces them to stay linked.

The workflow that works

A controlled claim process is not complicated. It is five habits, kept in one structure:

1. Fix the baseline

The contract BOQ — items, quantities, rates — is the reference for everything that follows. Every claim line points back to it. Extra work is added as separate, named items with their own descriptions, never mixed into original quantities.

2. Measure progress against the baseline

Physical progress is recorded weekly, against the same BOQ structure, by the people who see the work. Not a separate tracker with its own logic — the same items, the same units.

3. Derive the claim — don’t invent it

The monthly claim is produced from the progress record: cumulative value of work done, minus what was previously certified. If the claim needs a meeting to reconstruct what happened, the tracking has already failed.

4. Record the certificate as its own record

What the client certifies is entered alongside the claim, never over it. The gap between claimed and certified is not noise — it is the list of items to explain, correct, or resubmit.

5. Reconcile and carry forward

Executed, claimed, and certified stay as three linked, separate values per item. What was rejected or under-certified is visible and goes back into the next claim deliberately, not by luck.

Frequently asked questions

What is the difference between a progress claim and a payment application?

They are the same document under different names. “Progress claim” is common in the UK, Australia, and much of Europe; “payment application” or “pay app” is common in the US; “interim application” also appears in contracts. All of them mean the periodic statement of the value of work completed, submitted for payment.

What is the difference between a progress claim and a payment certificate?

The claim is what the subcontractor asks for; the certificate is what the client or main contractor accepts for payment. The two rarely match. They should be kept as separate records, because the gap between them — what was claimed but not certified — is exactly what needs to be explained, corrected, or resubmitted.

How often are progress claims submitted?

Usually monthly, as set by the contract. Physical progress, however, should be measured more often — typically weekly — so that the monthly claim is produced from an existing progress record instead of being reconstructed from memory at the end of the month.

Should extra work be included in a progress claim?

Yes, but as separately identified items with their own description and approval trail. Extra work merged silently into original contract quantities is the fastest way to lose entitlement: the client cannot certify what they cannot see, and the subcontractor can no longer prove what was original scope and what was added.

More guides

Freicore Product / Bearing

Bearing implements exactly this workflow.

BOQ/WBS baseline, weekly physical progress, timesheets, and progress claims with client certificates kept as separate, linked records. Built for construction subcontractors who control their own scope — if you only need invoicing, an accounting tool is the better fit.